UPS Installation Project by N.V. White Ltd  

The clients old UPS system consisted of 3 very large UPS systems. The batteries were failing within each UPS & required upgrading. We installed a brand new UPS system that not only was a lot smaller but cheaper to run & maintain also. We installed a new automatic transfer switch, mains cabling, UPS system & distribution board. The project was completed within 5 days & the downtime between the old & new UPS was around 6 hours.  
 
We provided the client with a back up UPS/ generator on site incase the main supply did have power loss & we had a team member onsite at all times incase that back up generator failed to ensure that another backup generator was on site in time so did not cause the client any disturbances to their work. 
 
 
 
 
 
 
 
 